Update for Week of April 11th

* On Monday, the mainline will be shut off on Broad for the day

* On Tuesday and Wednesday, the storm drain will be completed and there will be testing of the water across the Cedar and Broad intersection.

* All wet utilities will be completed during this week and will be moving off by the end of the week.

* The structure crew will be mobilizing mid-week to complete the storm drain structures. They will start at the junction box at Broad and Belt Line causing Broad to be closed during the days there is work being done.