Update for Week of August 8

* All parking on Broad St. has been completed

* Enhanced textures that will be on the intersection and crosswalk at Belt Line will be poured by mid-week.

* Excavation at the intersection of Cedar St. and Broad St. will begin this week to form the concrete for the enhanced textures on the walkway.

* All underground irrigation should be completed by the end of the week allowing for the contractor to start the sidewalk paving process.

* Updated traffic road closure in the image below: