Update for Week of July 25

* All of the main paving & parking on Cedar St. is complete, except for the transition by the railroad track.

* Contractor will be demoing all concrete next to the quilt shop. They will then pout the parking back at the quilt shop first to provide access from Cedar and Broad for parking, then the parking will be available.

* The irrigator is scheduled to mobilize this week to be installing piping in areas that they can access.