Update for Week of June 27

* This week, concrete will be poured at Belt Line Rd & Broad this week and prepared for the stamping of the pavement.

* Once the concrete is cured and stamped, then the construction will be flipped to Broad St and north of Cedar.

* Forms and rebar will be installed on the south side of Cedar St.

* Traffic patterns will remain the same as the previous week.