Update for Week of March 14th

* Sewer and sub main lines on Cedar St. have been completed.

* Storm and water lines will be worked on Broad St.

* Broad St will be closed to traffic between Cedar St. and Belt Line Rd from 7am - 5pm.

* Underground conduit work will be started on Cedar St.