Update for Week of May 31
* The main drive on Broad Street will be poured this week
* Excavation crew is working on Cedar St. The concrete crew will move into Cedar St. as they finish Broad St.
* Electrical crew has all pads and pull boxes in place beside the switch gears and transformer on Broad St.
* Traffic will continue to be interrupted.